Short answer
Test and record each string using the BS EN 62446-1 PV array test report in MIS 3002 Appendix E: module type and quantity, design Voc and Isc, measured Voc and Isc with irradiance, polarity, insulation resistance from positive and negative to earth, earth continuity where fitted, isolator ratings and functional checks, and inverter make, serial and function.
Last checked 24 September 2026 · 1 source
In more detail
- MIS 3002 cl.6.1.2: inspect and test to IET PV CoP Section 16 (except 16.4).
- Plus BS 7671 inspection/test of the AC side (IEC 60364-6 references on handover form).
- Keep records for periodic verification; full maintenance visits add series resistance, Riso, PID tests and thermography.