Short answer
No UK rapid-shutdown requirement like the US NEC rule was found in MIS 3002 issue 6.0, MIS 3002:2025 or the DESNZ plug-in specification. MIS 3002 does require any arc-fault detection function in the inverter to be enabled, and the emergency shutdown procedure must be displayed. Module-level power electronics remain a design choice for shading or firefighter concerns.
Last checked 24 September 2026 · 1 source
In more detail
- MIS 3002 v6 cl.5.6.7 arc-fault detection enabled where present.
- BS 7671 712 and IET CoP not searched (paywalled) - medium confidence.
- Module layout should allow access for maintenance and emergency services (cl.5.6.2).
The facts, dated
- 01Inverter arc-fault detection must be enabled where present — cl.5.6.7
standard · UK · checked 24 September 2026 · MCS