Is solar PV or battery installation notifiable building work?
Short answer
In England, yes whenever the work adds a new circuit, replaces a consumer unit or alters circuits in a special location, which covers most PV and battery installs. Notify through a Competent Person Scheme or building control before handover. MIS 3002 requires installers to agree in writing who notifies. Wales, Scotland and Northern Ireland have separate regimes.
Last checked 24 September 2026 · 1 source
In more detail
- Building Regulations 2010 reg 12(6A).
- MIS 3002 cl.5.1.6-5.1.7 (notification before handover where contractor responsible; new-build may hand over after commissioning).
- Roof works may engage Part A (structure), B (fire - in-roof kits, Appendix C), C (weathertightness).
The facts, dated
- 01Notifiable Part P work categories — new circuit; CU replacement; special location
regulation · England · checked 24 September 2026 · legislation.gov.uk