When must the MCS certificate be registered for a solar or battery install?

Short answer

No later than 10 working days after commissioning, the MCS contractor registers the installation on the MCS Installation Database and generates the MCS certificate, then sends it to the customer for the handover pack. Registration is only allowed once the system is fully installed and commissioned, and each registration carries a per-installation fee.

Last checked 24 September 2026 · 1 source

In more detail

  • MIS 3002 v6 cl.6.3.2-6.3.5.
  • Certificate is what SEG licensees and many schemes ask for as evidence (licensee-specific).
  • Register only after full install and commissioning - not before.

The facts, dated

  1. 01
    Deadline for MCS Installation Database registration after commissioning — 10 working days

    standard · UK · checked 24 September 2026 · MCS