Do I need MCS certification to get paid under the Smart Export Guarantee?
Short answer
Usually yes. For solar up to 50 kW, Ofgem says SEG applicants must show the installation and installer are certified - normally an MCS certificate, or an equivalent such as Flexi-Orb. Without it, suppliers are not obliged to pay you, although they may choose to. You also need a half-hourly export-capable smart meter.
Last checked 24 September 2026 · 1 source
In more detail
- Certification: MCS or schemes accredited to EN 45011 / ISO/IEC 17065
- British Gas accepts MCS, Flexi-Orb or accreditation certificate plus G98/G99 proof
- Export must be metered by a half-hourly-capable meter with an export MPAN - no deemed export under SEG
The facts, dated
- 01SEG: PV <=50kW needs installation and installer certification — 50 kW
scheme · GB · checked 24 September 2026 · Ofgem
- 02SEG export must be metered by a half-hourly capable meter with an export MPAN
scheme · GB · checked 24 September 2026 · Ofgem