SolarpunkHomes
Sign inCall us · +44 7510 081687
Solar
Solar · Error codes · SolarEdge
2x90SolarEdge · HD-Wave single-phase inverter (SE2200H-SE6000H)

2x90 on a SolarEdge HD-Wave single-phase inverter: Islanding - Passive: Grid is down. When AC grid voltage returns the inverter will restart after the reconnection time

Short answer

On a SolarEdge inverter, 2x90 means: Islanding - Passive: Grid is down. When AC grid voltage returns the inverter will restart after the reconnection time. The inverter stops until the fault clears or is reset.

Reviewed 24 September 2026 · 1 source

What it means

The manual says: Islanding - Passive: Grid is down. When AC grid voltage returns the inverter will restart after the reconnection time.

Part involved: Loss-of-mains / anti-islanding.

Likely causes:

  • Power cut / loss of mains.
  • AC breaker or isolator off.
  • AC grid voltage malfunction.

Is it safe?

Does the inverter stop?Yes
SeverityFault — clears by itself when the condition goes

The inverter stops until the fault clears or is reset.

Resetting itself: yes - restarts after the reconnection time once mains returns.

Manual reset: no.

What you can check

  • Read and note the exact code and time from the inverter display or app (screenshot).
  • Check whether there is a power cut (other lights/sockets, DNO 105 service).
  • Check the solar/battery AC isolator and the consumer-unit breaker/RCD are ON (do not reset a breaker that trips again immediately).
  • If the code persists, contact the installer. SolarEdge's list says 'OFF/ON to reconnect' for some codes - that means the inverter's own ON/OFF switch; only use it if your installer has shown you how. Never open the inverter or touch DC cables/connectors.

What the engineer will check

  • Check AC isolator, breaker and terminations at the inverter.
  • Measure L-N voltage at inverter terminals.
  • Check neutral connection.

Who to ask for: PV installer / electrician.

Certification: Electrician competent in grid-connected PV (BS 7671 Section 712; IET Code of Practice for Grid-connected Solar PV), ideally the original MCS-certified PV installer; brand-approved/trained installer to keep manufacturer warranty.

What you might notice

Sources

A code explains what the controller detected, not a confirmed root cause.

Reviewed: 24 September 2026