18x3BSolarEdge · HD-Wave single-phase inverter (SE2200H-SE6000H)

18x3B on a SolarEdge HD-Wave single-phase inverter: I-ACDC: AC overcurrent (I-ACDC L1/L2/L3); if flagged on all three phases at once, most likely a DC-related issue on site

Short answer

On a SolarEdge inverter, 18x3B means: I-ACDC: AC overcurrent (I-ACDC L1/L2/L3); if flagged on all three phases at once, most likely a DC-related issue on site. The inverter stops until the fault clears or is reset. An engineer is needed to fix the cause.

Reviewed 24 September 2026 · 1 source

What it means

The manual says: I-ACDC: AC overcurrent (I-ACDC L1/L2/L3); if flagged on all three phases at once, most likely a DC-related issue on site.

Part involved: Inverter internal hardware / firmware.

Likely causes:

  • DC string issue (improper installation/stringing).
  • Inverter fault.

Is it safe?

Does the inverter stop?Yes
SeverityFault — needs a manual reset once the cause is fixed
Engineer needed?Yes

The inverter stops until the fault clears or is reset.

Resetting itself: sometimes clears after a restart; recurring = hardware fault.

Manual reset: restart; otherwise replacement.

What you can check

  • Read and note the exact code and time from the inverter display or app (screenshot).
  • Check the solar/battery AC isolator and the consumer-unit breaker/RCD are ON (do not reset a breaker that trips again immediately).
  • If the code persists, contact the installer. SolarEdge's list says 'OFF/ON to reconnect' for some codes - that means the inverter's own ON/OFF switch; only use it if your installer has shown you how. Never open the inverter or touch DC cables/connectors.

What the engineer will check

  • Restart per manual.
  • Update firmware.
  • Contact manufacturer support with serial number; RMA if repeated.

Who to ask for: PV installer with manufacturer support access.

Certification: Electrician competent in grid-connected PV (BS 7671 Section 712; IET Code of Practice for Grid-connected Solar PV), ideally the original MCS-certified PV installer; brand-approved/trained installer to keep manufacturer warranty.