Does adding a battery change the network application?

Short answer

Usually yes. The battery's inverter counts toward the same 16 A per phase limit as your solar, so a 3.68 kW solar inverter plus a separate battery inverter normally needs G99 approval before installation. A single hybrid inverter can keep the total within G98 if its output is limited to 3.68 kW.

Last checked 24 September 2026 · 1 source

In more detail

  • MIS 3002 5.1.9 note example: 3 kW PV + 3 kW battery on single phase exceeds 16 A so G99 applies.
  • G98 aggregates all inverters at one connection point.

The facts, dated

  1. 01
    3 kW PV plus 3 kW battery on a single-phase supply exceeds 16 A so EREC G99 applies (MIS 3002 example)

    standard · GB · checked 24 September 2026 · MCS