F29 on a Toshiba heat pump: EEPROM failure (hydro unit)

Short answer

On a Toshiba heat pump, F29 means: EEPROM failure (hydro unit). The heat pump stops until the fault clears or is reset. An engineer is needed to fix the cause. The wording differs by model range — each is shown below.

Reviewed 23 September 2026 · 4 sources

What it means

On the R32 Estia 1-Series (split, Wall-Mounted and All-in-One)

The manual says: EEPROM failure (hydro unit).

Part involved: water heat exchange control board.

When it shows: Hydro unit EEPROM fault.

Likely causes:

  • Replace hydro unit P.C. board.

On the Estia (Series 4) Standard & Powerful

The manual says: EEPROM error.

Part involved: water heat exchange control board.

When it shows: EEPROM write verify failure.

Likely causes:

  • Replace water heat exchange control board.

On the Estia 5 Series (Standard)

The manual says: EEPROM error.

Part involved: water heat exchange control board.

When it shows: EEPROM write verify failure.

Likely causes:

  • Replace water heat exchange control board.

On the Estia 5 Series Powerful (Hi Power / Extreme)

The manual says: EEPROM error.

Part involved: water heat exchange control board.

When it shows: Trigger thresholds not printed in the IM; see SM.

Likely causes:

  • Replace water heat exchange control board.

Is it safe?

Does the heat pump stop?Yes
SeverityFault — needs a manual reset once the cause is fixed
Engineer needed?Yes

The heat pump stops until the fault clears or is reset.

Resetting itself: no.

Manual reset: Cause must be fixed by an engineer; hardware faults reappear until repaired.

What you can check

  • Note the check code shown on the remote controller and the outdoor/hydro model numbers before contacting an engineer.
  • Check the consumer-unit breakers/isolators for the outdoor unit, hydro unit and backup heater are switched on.

What the engineer will check

On the R32 Estia 1-Series (split, Wall-Mounted and All-in-One)

  • Follow manufacturer's check-code flowchart.
  • Replace hydro unit P.C. board.

Who to ask for: Heat pump engineer.

Certification: Electrical competence.

On the Estia (Series 4) Standard & Powerful

  • Follow manufacturer's check-code flowchart.
  • Replace water heat exchange control board.

Who to ask for: Heat pump engineer.

Certification: Electrical competence.

On the Estia 5 Series (Standard)

  • Follow manufacturer's check-code flowchart.
  • Replace water heat exchange control board.

Who to ask for: Heat pump engineer.

Certification: Electrical competence.

On the Estia 5 Series Powerful (Hi Power / Extreme)

  • Follow manufacturer's check-code flowchart.
  • Replace water heat exchange control board.

Who to ask for: Heat pump engineer.

Certification: Electrical competence.