1101 on a SMA Solar Technology AG Sunny Boy: A second line conductor is connected to N

Short answer

On a SMA Solar Technology AG inverter, 1101 means: A second line conductor is connected to N. The inverter stops until the fault clears or is reset. An engineer is needed to fix the cause.

Reviewed 24 September 2026 · 1 source

What it means

The manual says: A second line conductor is connected to N.

Part involved: AC wiring / country data set.

When it shows: A second line conductor is connected to N.

Likely causes:

  • SMA corrective measures: Connect the neutral conductor to N.

Is it safe?

Does the inverter stop?Yes
SeverityFault — needs a manual reset once the cause is fixed
Engineer needed?Yes

The inverter stops until the fault clears or is reset.

Resetting itself: no.

Manual reset: See engineer checks.

What you can check

  • Read the event number and message in the SMA Energy app / Sunny Portal (ennexOS) or the inverter's web interface and note the date/time for your installer. A red LED on the inverter means an event has occurred.
  • This points to an installation/configuration issue - contact your installer; do not attempt wiring checks.

What the engineer will check

  • Check PE/earth, L/N polarity and neutral connection at the inverter and feed-in meter; check country data set (Grid Guard code needed to change); restart self-test where applicable.

Who to ask for: Electrician / PV installer.

Certification: Qualified electrician (BS 7671; MCS-certified PV installer for work on the PV array/DC side).

What you might notice

Sources

A code explains what the controller detected, not a confirmed root cause.

Reviewed: 24 September 2026